New Building Update
Construction Updates
We’ve Moved in!
-
- A 2 story, 35,000 square foot building
- 24 exam rooms
- Two larger treatment rooms
- 6 surgery suites
- 4 dental tables
- A separate clinic upstairs to ease stress for our feline friends
- A Bereavement Room to help beloved pets cross the rainbow bridge
- Separate entrances for highly contagious diseases
- Plenty of space and hospitalization wards to separate all categories of illness.
- So much more!
May 10, 2024: Expanding Our Client Parking
With our old building demolished and all debris cleared out, the construction company has smoothed and prepared the ground for our new expanded client parking lot. The storm drains have been installed and the area is now ready for the parking lot to get poured.
December 15, 2023: Final Checks and Stocking The New Hospital
With majority of our construction finished, the contractors are doing a final check over the building to make sure everything is working and polished up. Our team is preparing and stocking the new hospital with all of the necessary supplies while we wait for a crucial final part of our generator.
November 3, 2023: Security Cameras, Diagnostic Equipment, Kennels, Furniture, and Final Touches.
As things are nearing completion, the construction company has been working on the final touches around the new building. The furniture was delivered earlier this week and is being set up in its designated areas. The TV monitors, security cameras and access control have been installed throughout the building. All the kennels, including the specialty isolation and oxygen cages, have been put in on both floors.
September 29, 2023: Floors Nearly Complete, Fire Alarm System, Computers and TV Monitors, Reception Desks, Kennels, Pet Rehab, and More!
With the building almost complete, the construction company has been busy wrapping up some big projects! The epoxy flooring has been finished on the second floor and they are working on the last half of the first floor. The fire alarm system has been installed throughout the hospital, along with the oxygen and anesthesia wall ports. The computers and TV monitors are being hooked up in their designated locations. Both reception desks, for the main lobby and 2nd floor feline medicine, have been put together and are nearly ready to use.
August 25, 2023: HVAC, Front WPAH Sign, Epoxy Flooring on the Second Floor, Pneumatic Tube Systems, Front Lobby Desk’s, Door Frames, and So Much More.
With full power now connected and working, the construction company has been able to install the HVAC systems and we now have working air conditioning. They have also started balancing the air flow throughout. The pneumatic tube systems between the 1st and 2nd floors for the pharmacy and in-clinic laboratory are nearly complete. The front desk and treatment tables for feline medicine have been put in. They have begun to pour epoxy flooring around the second floor and finishing the final coat of paint before starting on the first floor.
They have begun installing the surgery and treatment lights throughout the entire hospital. The computer wall mounts have also been put up in the exam rooms. With flooring in the data center complete, they have begun installing the server racks and network cabinets. They have also started putting in the remaining window and door frames, as well as putting in the 1st floor front desk.
July 21, 2023: WE HAVE FULL POWER! Installing Cabinets, Elevators, Ceiling, Lights and Backup Generator! Exam Tables, Kennels, Oxygen Cages Have Arrived! Prepping Second Floor to Pour Epoxy.
The construction company and contractors have made a lot of exciting progress in the past month! We now have complete power to our new facility and are working on installing our backup generator. The delivery doors and walk-in freezer have been set-up and are functioning. The cabinets, elevators, ceilings, and lights are currently being installed.
June 16, 2023: Painting the Interior, Installing Cabinets and Interior Window Frames, Exterior Walkways, and More!
The construction company has been busy this past month painting the interior walls, installing the decorative lighting in the main staircase, and putting up the wall tile and ceiling grids throughout the building! The interior window frames and another shipment of cabinets have arrived, and are currently being installed.
May 18, 2023: Exterior Nearly Finished, Drywall on the First Floor, Cabinets and Wall Tile Arrived!
The construction company is just about complete with the final touches on the exterior of the building. They are currently installing the outdoor lighting and open downspouts. The remaining logo signage on the exterior is now complete and ready to light up the night!
April 14, 2023: Exterior Composite Panels & Window Frames Finished, Prepping for Paint Primer on the Second Floor, First Floor Insulation & Drywall has Started, and Elevator Parts Arrived.
The construction company has finished installing all of the accent composite panels and window frames around the building! They are almost done inserting the glass into the window and door frames.
March 10, 2023: Installing the Exterior Metal Accents, Finishing the Window Frames, and Putting Up Drywall on the Second Floor.
The construction company is officially finished with the exterior bricks and has begun installing the metal accent pieces around the outside. They are almost done installing the window frames around entire building and inserting the windows. The construction company also put up the signage on the North wall above the future entrance to the building.
February 10, 2023: Installing Windows, Building Signage, and Putting Up the First Floor Metal Wall Studs.
The construction company has been hard at work on the exterior of the building finishing up the bricks along the outside. The signage on the front of the building is now up and awaiting electrical connection. With most of the window frames installed, they have began inserting the glass as well!
Inside, the metal wall studs have been put in on the first floor, giving us a real feel for what’s to come! We are eager watch as this space continues to be transformed.
December 23, 2022: Laying the Bricks, Installing Electrical, HVAC, Sprinkler Systems, and More!
November 4, 2022: First Floor Concrete Finished, Interior Wall Framing Going Up, and Exterior Waterproofing!
October 14, 2022: Second Floor Concrete Finished and Exterior Walls Going Up!
September 23, 2022: Pouring The Concrete, Preparing for the Roof, and Framing the Windows!
August 26, 2022: Preparing for the Roof and 2nd Floor Plumbing!
August 12, 2022: Exterior Wall Studs and Finishing up 1st Floor Plumbing!
JULY 29, 2022: Starting The Plumbing and Exterior Wall Studs!
JULY 14, 2022: Wrapping Up Deck Welding and Installing the Stairs!
JULY 1, 2022: Putting up the Metal Decking!
JUNE 17, 2022: Noticeable Changes with Framing!
JUNE 3, 2022: Putting Up The Steel Frame!
May 13, 2022: Pouring The Stairwell Concrete!
April 29, 2022: Finishing Up The Elevator Shaft and Stairwells!
April 15, 2022: Bringing in the Building Blocks!
The construction company is full steam ahead! As more cinder blocks arrive, the elevator shafts and stairwells go up!
April 1, 2022: Finally, Foundation Time!
ABOUT US
Thank you for your Cleveland Hot List votes. We were voted #1 again for the 5th year in a row! We are happy to continue to serve the community and appreciate your support.